CDS 4.8.0 Release delayed to 14th June 2025

CDS 4.8.0 Release delayed to 14th June 2025

16 May 2025


CDS Release 4.8.0 will no longer be delivered on 31st May 2025. The new date for deployment of this Release will be 14th June 2025.

Any pre-lodged declarations that are expected to arrive between 31st May 2025 and 13th June 2025 should continue to be completed in line with the current Declaration Completion Instructions.

Any pre-lodged declarations due to arrive after the 14th June 2025 that will be affected by the changes in Release 4.8.0 will need to be amended before goods arrival in order to avoid rejections.

Please find attached an updated version of the Release Guidance for CDS Release 4.8.0. The only change from the previously-issued document is the new date for the Release.